October 13th, 2005
The site for the new Indoor Facility is leveled to excavation depth.
October 17th, 2005
Crews work on placing the first lift of subbase.


October 28th, 2005
Excavation begins on the footings for the Cover-All building that will house the new indoor soccer field.

November 7th,
Heavy equipment moving dirt for parking lot and future outdoor field at Marshall.

November 8th,
Footings being formed up for Cover-All building.

November 10th,
First concrete on site.


November 21st, city crews relocate waterline to new clubhouse.


Grant and Matt Goldie finishing the footings and frost walls for the entrance to the new clubhouse at Marshall Field.

November 30th, Cover-All crews installing the first steel for the new Cover-All building.



Construction of the lobby area in the new clubhouse starts Dec, 1st.































The Vernon Soccer Association proudly announces

The Indoor year-round Soccer Facility
will be situated at the Marshall Field Complex in the Okanagan Landing area
With support from Greater Vernon Services (GVS) the
VERNON SOCCER ASSOCIATION IS
“Dedicated to continued soccer growth & development for our youth”
THERE ARE MANY WAYS YOU CAN SUPPORT THIS PROJECT
WE ARE LOOKING FOR:
- CASH DONATIONS
- IN-KIND SERVICES / CONTRIBUTIONS
- ADVERTISING
For more information about these options please contact one of the below:
North Okanagan Youth Soccer Office @ 545-5808 Email:noysa@telus.net
Box 1390 Vernon BC V1T 6N7
or
Darrell Buckham @ 545-9188
PLEASE BE PART OF THIS PROJECT